INSTALLATION AND FUNCTION TEST.
Reduce risk and ensure reliable installation and equipment performance.
When you rely on the expertise of T Arrow to commissioning your new equipment, you protect and enhance your equipment investment. No one else is more qualified to inspect and test your equipment prior to energize to verify it is free of damage during shipment and installation, and has been properly installed. This will help ensure trouble-free start-up and long-term performance.
- Electrical Systems Analysis
- Electrical Distribution Designs
- Power Quality Correction
- Power Management
- Equipment start-up
- Operation and maintenance training
- Project management
PREVENTIVE MAINTENANCE.
Prevent shut down with predictive maintenance.
Whether you need routine maintenance or emergency response, you can count on T-Arrow. Service for full-service, We service most major manufacturers' electrical equipment.
- Maintenance program
- Cable testing
- Switch gear
- Protective relay
- 24-Hour emergency service
- Infrared testing
- On-Site maintenance
Scope of work.
Inspection
- General condition check.
- Body and seal check.
- Termination check.
- Mechanism condition check.
- Earthing and grounding check.
- Interlocking operation check.
- Shutter and partition check.
- Indicator status check.
- Insulator post check.
Testing
- Insulation resistance test.
- Contact resistance test.
- Operation and function test. (Manual / Electrical)
- Motor driving test. (If have)
- Check trip function by simulate the trip signal from safety interlocking / or protective relay.
Improvement / Treatment
- Cleaning and re-lubricating the operating mechanism.
- Auxiliary / limit switch treatment.
- Contact surface treatment.
- Mounting tightening and treatment.
- Pole and gripping contact treatment
- Cubicle / racking cleaning.
- Operation the disconnect switch several time (3-5 times) to make mechanism movement.
- Insulator post cleaning.
Inspection
- General condition check.
- Body and seal check.
- Termination and mounting check.
- Parameter checking and recording of protective relay.
- Adjustment / Knob check.
Testing
- Time characteristic test.
- Relay testing function. (By test trip mode)
- Relay testing function. (By secondary injection)
- Indicator / display test.
Note: Testing at parameter service value.
Improvement / Treatment
- Adjustment.
- Panel and body cleaning.
- Contact cleaning.
Test report and Comments
- By T Arrow
Inspection
- General condition check.
- Body and seal check.
- Termination check.
- Mechanism condition check.
- Earthing and grounding check.
- Gas indicator check. (if have)
- Interlocking operation check.
- Shutter and partition check.
- Pole and gripping condition check.
- Indicator status check.
Testing
- Insulation resistance test.
- Contact resistance test.
- Operation and function test. (Manual / Electrical)
- Motor charging test. (If have)
- SF6 Gas leakage test.
- Check trip function by simulate the trip signal from safety interlocking / or protective relay.
Improvement / Treatment
- Cleaning the circuit breaker and re-lubricating the operating mechanism.
- Auxiliary / limit switch treatment.
- Rack-in / rack-out circuit breaker cleaning.
- Contact surface treatment.
- Tightening bolt and nuts.
- Pole and gripping contact treatment.
- Cubicle / racking cleaning.
- Operation the disconnect switch several time (3-5 times) to make mechanism movement.
เครื่องกล สื่อสาร
แรงสูง แรงต่ำ
จำหน่ายไฟฟ้า MEA, PEA
และ solar cells
แสงสว่างและไฟ
ตัวอย่าง ผลงานของเรา
